I am trying to sort a smartsheet where I have some rows at the top that are used for calculations and formulas, so I only want to sort certain rows not all of them.   Is there a way to do this?   I tried locking those rows but that doesn't work, and I tried just highlighting just the rows I want

5

I don't know if it is bug or feature, but it looks strange for me.

 

So I have sheet created based on project template. I have dependency turned on.

 

I noticed next behaviour: If task start at weekend or holiday then duration calculated with one extra day. On attached image all tasks (except task2)