Webforms
Hello. When I create a new webform and have 'use a custom label' checked the associated sheet does not show the custom label name. Is this a bug?
-
Counting Number of Times a Predecessor is Used
Hi, Long story behind this one, I'll try to keep it short. On Smartsheet, the critical path tool isn't working for my sheet because our project has too many hard deadlines and we are not using enough predecessors; however, we need to be able to view a critical path, so I have accepted that I will have to create one…
-
Best Practice for Backing Up
My project management team joined Smartsheet about 6 months ago and have created quite the plethora of sheets. All of them are in use as we are managing a very large project, so I do not want to delete any (and as we have so many paid users, we are far from our sheet limit) and they are all dynamic/active sheets. However,…
-
Only print the milestones on my gantt
Hi, I'm new to smartsheet. My project is large. How do I print the grantt that only has the milestones and not all the data? Thanks Donna
-
Smartsheet Merge - Merge Data Speed/Failure
I imported a word doc that I had been using in an existing merge that had a relationship with an excel doc. (I broke the relationship before importing into Drive) I copied the word doc into a google doc. I then started Smartmerge and mapped all the fields to the Smartsheet. I clicked Run Merge and it's just spinning,…
-
Universal Conditional Formatting Across All Sheets
Hi, Is there way to have a conditinal format rule apply across an entire database? For exampe, i have a collegue whose name I want to highlight in yellow so it it easy to see on any project (sheet) he is working on. I want to avoid adding the conditional formatting rule to each sheet he appears on. Is it possible to make…
-
Dependencies - with time between items
This is the senario: Line 1: Start date January 1st. Duration 5 days Line 2: Start date January 15th. Duration 5 days. I want the two lines to be dependent so that line 2 can't start before line 1 is done. However, Line 2 should not start before the 15th. My problem is that if I create a dependency, the startdate of line 2…
-
Notifications
Hi All, I have a list of salesmen on a sheet of warranty information. Is it Possible for these individual salesmen to get an email only related to changes made to their customers only? Another way of putting it is can a daily notification email be sent based on the salesmens name in the field once a day to that salesman…
-
Conditional lock
Hello, I am trying to develop a shareable sheet in which some tasks are listed along a row and check boxes are used to indicate a task has been completed. Would it be possible to lock these checkboxes if its previous one haven't been checked? In this way a process flow would be enforced. Perhaps the solution would include…
-
Copy Conditional Formatting Rules
Hi, I tend the same conditional formatiing rules across several Workspaces and sheets. Is there a way to copy the rules so I can use them on new sheets? Thanks.