An idea is simple. There is a column "Finish" defined as date column. and % Complete column.
What i need to do is to highlight the risk if Finish is past due or lesser then Today and % complete is below 100.
Here is the formula: =IF(AND([Finish] < TODAY(), [% Complete] < 100%)), "At Risk", "--""))
I tried % complete being 1, 100% and 100 with the same result
The link to the doc: (8) EBD1 SAP ECC Stream - Smartsheet.com. Please help. I need it urgently. Thank you.