Change the number of working day manually
phulq
✭
My project team work on Saturday then next week we are off on Saturday. That cycle keeps going like that. How can I describe that and update in calendar in smartsheet? Thank you!
Comments
-
If I understand you, you mean that you team work Alternate Saturdays?
In the Project Settings set Saturdays as working then enter Every other Saturday as non working. Not neat and simple but works.
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- 10.7K Get Help
- 63 Global Discussions
- 69 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives