Hi There
I'm very new to smartsheet so for you this might be a very simple thing. I'll appreciate if someone let me know what'd be the formula if I want to raise a flag whenever the due date is 30 days from the current date. We'll appreciate your help.
Thanks
Raashid K
Comments
-
I'm not using the flags because my viewers tend to overlook them. I'm using Conditional Formatting so the Finish Date (Due Date) cell is highlighted. Sample below.
"If Finish Date is in the next 30 days then apply this format to the Finish Date column"
Hope this helps.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- 10.7K Get Help
- 63 Global Discussions
- 69 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!