export schedule to XML, the dates got moved

Datouyu
Datouyu ✭✭
edited 12/09/19 in Smartsheet Basics

Hi There, 

 

When I export schedule from Smartsheet to XML file and open XML file in Microsoft project, the dates of some tasks got moved. 

Has anybody had the same problems and possible ways to fix it? 

 

Dale Dai

 

Comments

  • Genevieve P.
    Genevieve P. Employee Admin

    Hi Dale,

    Because Smartsheet and Microsoft Project differ in their functionality, the exported sheet may display differently in either application. (Read more about exporting to XML here.)



    For the dates that were affected, you may want to copy the data from Smartsheet and paste it into your XML file using keyboard shortcuts Ctrl+C and Ctrl+V (Windows) or Command+C and Command+V (Mac).

    Cheers,

    Genevieve