Formulas in Columns with Dependencies?

03/28/18 Edited 12/09/19

Is there any way to work around dependencies in columns when entering in formulas? 

Popular Tags:

Comments

  • Chris McKayChris McKay ✭✭✭✭✭

    Hi Aoaks,

    Are you referring to a dependency column in a project sheet (i.e. the column linking task predecessors/successors)?

    If so, no there is no way to get around this, as Smartsheet actually uses hidden formulas in project columns to calculate values.