Resource Allocation
Shanett Cole
✭✭✭✭
Can you assign Resource Allocation for the entire project vs. only assigning per task on each line with % allocation
Shanett is only 50% on the prj
Sally is 100% on the prj
Comments
-
I believe, Shanett, that you have to do this per task (row).
To make it quicker, filter on Shanett and copy/paste the 50% to all the tasks allocations.
Craig