%Complete to be automated
Comments
-
Hi there!
I am fairly new to Smartsheet as well and I used logic similar to excel and did a countif and then divide it by a total count. I used checked boxes for each step and it would update my % Complete for me.
Here is the formula that I utilized, but there might be something simpler that I am not aware of.
=(COUNTIF([Scope Complete]2:Done2, <>0) / (COUNT([Scope Complete]2:Done2)))
-
Good Morning,
I just tried it and it is not working for what I am looking to do I have target date and completion date. When I change the information in the formula tabs it comes up with the Unparsable error
-
I wasn't using dates -but you could create a column that gives you the total days and the total remaining days based on the target. I am sure you could do this in a formula as well. My formula was looking to see if multiple columns were greater than 0.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- 10.7K Get Help
- 63 Global Discussions
- 69 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives
Check out the Formula Handbook template!