Finish-to-Finish Dependency pushing finish date out past its predecessor
I'm trying to create a finish-to-finish dependency between two rows in a sheet so that the two rows share a finish date. However, when I add this dependency in, the finish date of the dependent task is pushing out months past the finish date of the predecessor.
Has anyone else seen this behavior? Is there something I'm missing?
Comments
-
Hi Brian,
I tested this and it worked as expected. I would suggest looking to see if there are other predecessor relationships in place that may be causing this behavior, but please continue to work with our Support team and feel free to update us with the resolution.
-
Any update on this?
-
Hi @Melea
Can you clarify your question and scenario? It would be helpful to see a screen capture of your project plan and an explanation of what you're seeing (vs. what you would like to see), but please block out sensitive data.
Thanks,
Genevieve
Categories
- All Categories
- 14 Welcome to the Community
- 10.7K Get Help
- 63 Global Discussions
- 69 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives