Gantt Task Completion bar based on dynamic % Complete
Ben Donahue
✭✭✭✭✭
Is there a way to set a dynamic column to be the % Complete column for the purpose of setting the Task Completion bar?
All help is appreciated.
Tags:
Comments
-
Hi Ben,
To accomplish this, open the Project Settings on the sheet and set the % Complete Column drop-down list (under Options) to reflect the column you've assigned as the % Completed Column.
If needed, more information on this can be found in our help article: https://help.smartsheet.com/articles/765737-project-sheet-columns-start-date-end-date-duration-complete-and-predecessors#Complete
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- 10.7K Get Help
- 63 Global Discussions
- 69 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!