I have a large MS Project file with almost 2000 lines and need it to be imported into smartsheet. While doing the automatic import, it seems many of the dates are shifted for an unknown reason and I am wondering if anyone else has experienced this. Is there a workaround or will I have to manually input this project file's data into smartsheet?

Department

Comments

Hi Mindy,

Sound like you need to change the project settings in the sheet. Have you done that after the import?

Hope that helps!

Have a fantastic week!

Best,

Andrée Starå

Workflow Consultant @ Get Done Consulting