Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Project Resource View
Comments
-
Jessica
By careful design you can have a range of ways to review your resources schedule.
In the sheet itself via the Red man, In Reports that summarise what each resource's tasks are in a list view, with the ability to interrogate via the Red man when that is helpful.
Or via the Home Button Resource View. Don't forget you can create filtered views for different teams.
You can even track your non human resources like a Training room as long as you can give it a "fake" email address.
So not sure what you are missing from this? If you need more, then we do offer a Free initial 1 hour consultation and can provide advice on Best Practice if needed?
Hope that helps
RichardR
Smarter Business Processes
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- 10.7K Get Help
- 63 Global Discussions
- 69 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives