can you provide more details about what you are trying to do?
-
Hi...I have the same question...
I typically manage or consult on multiple interdependent projects. I've tried managing dependencies across projects in different ways but none of them have been super successful.
For example, Project A - call it Telephone installation - has a dependency on Project B - call it, Network Infrastructure upgrade. They are being managed as two separate workstreams because of their content and resources, but at some point, work on project A will stop if Project B hasn't reached a certain point (usually a milestone).
I would like to (in the best case) show the dependency actually in the dependent project so that Project B is late, the remaining tasks of Project A slip. Alternate would be okay if I could just report on the dependencies and highlight pending problems.
Any suggestions would be appreciated...
Rob