I am trying to create a resource management sheet to show who of my resources is busy or not and what his utilization % is. My resources travel to locations and i would like to be able to see in resource view the time that is being used for travel separately from the class time. 

Appreciate your help,

Aldina 

 

Functionality
Department

Comments

Hi Aldina, have you thought about using a seperate sheet just for travelling time.  The time spend travelling and class time would then be shown seperately in the Resource View.

Mick

In reply to by Mick Jordan

Thanks @Mick Jordan

I guess.. but that means having to build a new sheet from scratch... frown or is there a formula that I can do something like ..if the location is not .YXZ..then duration (whatever on the duration column)+6hours? (Not an excel expert tho..) 

- still, the resource view uses start and end time not duration..i think. 

Any thoughts?

Thanks Mick.