Specifying task durations in months

Options
Jerry Tutt
Jerry Tutt ✭✭✭
edited 12/09/19 in Archived 2016 Posts

This may sound like a foolish questions..... I specify my task durations in days.  Can I specify some of them in months?  The reason I ask is that I noticed that when I enter a duration as 6 it displays "6d" for 6 days.  We have a number of tasks that have contractual commitment in 3 months.  Therefore, the need to be able to specify in terms of months.  

Comments

  • J. Craig Williams
    J. Craig Williams ✭✭✭✭✭✭
    Options

    Jerry,

     

    The closest you have is either 4w (4 weeks) or more accurate most of the time would be e91d for 3 months.

     

    The "e" tells it to ignore non-working days so this is 91 calendar days (pretty close to 3 months)

     

    Note that 91d without the "e" is work-days so 18+1 work-weeks, not 13 for a quarter.

    Contrarily, "4w" is only 20 working days (for a 5 day work week) and is not equal to 28d

     

    Hope this helps.

     

    Craig

     

  • Jerry Tutt
    Jerry Tutt ✭✭✭
    Options

    Thanks, Craig!  I will look at this more closely.  It sounds like a good possibility.

     

    Thanks, again...