Gantt Charts

Discussion List

  • Can I hide predecessor lines in a gantt chart?
    In Using Smartsheet
    I have a complicated project with tons of predecessors.  The predecessor lines connecting tasks in the gantt view are so numerous that is makes the gantt visually hard to use.  Is there are way to hide or turn off not the predecessors, but…
    579 6
    579 views 6 comments Most recent by Aaron Hillyer Using Smartsheet
  • Wrong Date line
    In Using Smartsheet
    Hi guys, Struggling with what I assume is a easy fix. The dotted line that represents 'today' is showing to be out by 1 day. I.e, it is Tuesday here, however the dotted line is showing Monday. I have been into user settings and ensured …
    45 3
    45 views 3 comments Most recent by Sean Morgan Using Smartsheet
  • How to default your view setting
    In Using Smartsheet
    Hello Smartsheet community,   I am wondering if there's any way to default your view setting to Gantt (or others) when you created a new blank sheet? I want to avoid changing the view setting every time my team and I are going into the s…
    859 7
    859 views 7 comments Most recent by Andrée Starå Using Smartsheet
  • Filtering for critical path to a milestone
    In Formulas and Functions
    Hi everyone, I have a project that spans multiple years and contains many workflows.  I would like to be able to track the critical path to different milestones (not just the last task in the sheet).  Are there any tricks to doing this in …
    32 2
    32 views 2 comments Most recent by Warren Humphrey Formulas and Functions
  • Gantt View Timeline color coded by stages
    In Using Smartsheet
    I am looking to develop a Gantt view that shows multiple colors on a single bar, based on the calendar, and corresponding stage of the project at that time. For example: Project XYZ, single timeline: red during planning stage (Oct 7-14), g…
    Answered - Pending Review
    15 1
    Answered - Pending Review 15 views 1 comment Most recent by Andrée Starå Using Smartsheet
  • Gantt charts and Dashboards
    In Using Smartsheet
    Hi.  new here to the forum; recently created a Smartsheet Gantt chart and subsequently integrated it into a Smartsheet Dashboard. Looks great except --- I seem to have lost my indentation of my subtasks under a parent task, and that makes…
    309 4
    309 views 4 comments Most recent by @Marino Anderson Using Smartsheet
  • Volunteer Allocation
    In Formulas and Functions
    Hi All,  I am attempting to find a solution for a specific manual task that is error prone and very time intensive - We need about 300 volunteers occasionally on short notice and need them across multiple cities in 20-50 specific location…
    62 3
    62 views 3 comments Most recent by Brianne Laird Formulas and Functions
  • Gannt chart start date does not match the date column
    In Using Smartsheet
    (Image) Hi, Pretty long project, spanning a bit over a year. I'm about halfway through it & the Gannt Dates started getting weird. In the image, Look at "Floors", predecessor 232. The scheduled start date column says 8/13, …
    Accepted
    21 3
    Accepted Answer 21 views 3 comments Most recent by itsnotbroken Using Smartsheet
  • Copy&Paste with relative predecessors
    In Using Smartsheet
    Hi, I have a schedule (created from Project template (aka Gantt chart)) where I have a section which is repeating several times in the schedule. Inside of a section I have dependencies linked using Predecessor field which do not point out…
    267 3
    267 views 3 comments Most recent by AmandaM Using Smartsheet
  • Formula to calculate date
    In Formulas and Functions
    Hello, I am trying to work backwards but I just don't get it. My event date is my constraint, I want some tasks to be completed x days prior to the event and Smartsheet to calculate the start date of the tasks automatically. For example, …
    Accepted
    12 3
    Accepted Answer 12 views 3 comments Most recent by Berenice Vanderley Formulas and Functions