Is there a way to set a constraint on a task's Start Date that can override a predecessor?
We have migrated a fairly complex plan from MS Project to Smartsheet and have been able to line up most of our dates. However, when Predecessors finish early on a task, the start date is impacted, as…1 · -
Re: Elapsed Days in Predecessor Field
Smart sheet does not seem to allow for ELAPSED TIME in predecessors such as 3FS+e4d. IT does allow for it in durations. This creates difficulties in creating timelines when production activities (7 d…4 ·