1

I've sent a series of Update Requests to external emails and I've had about 50% response rate.  I have had someone check the validity of the remaining email addresses and we've found several of the email addresses are no longer valid (they don't exist) and several others are issuing Out of Office

3

I currently have weekends blocked out in the dependency settings/working days.  However If we get behind on the schedule and decide to work a weekend to catch up, how do I add back in a single weekend.

I use predecessors to keep the project in the right order of operations.  If I manually fill in a

10

Hello everyone!

I'm a project coordinator at a company specialized in manufacturing and installing irrigation systems, we have over 50 projects going on at the same time.

We're trying Smartsheet to check whether it suits our needs, we're looking for a way to let a user supervising the project to