1

Hi there,

Okay, so here's what I'm trying to do. Our team is using a smartsheet schedule and within that schedule, is a bunch of sub-schedules, that all work together in glorious harmony :)

Up until now, I've been able to use the Predecessors column with ease, for e.g. 1FS + 5d, meaning that the

0

Olá, foi o possível substituto do modo de exibição da planilha doce? 

a Planilha é compartilhada, mas todo usuário tem sua função e visualiza o conteúdo de forma, porém, cada mudança, por exemplo, no tamanho da barra, altera para todos os usuários, sendo que essa alteração é tão séria necessário

2

I have 140 or so projects I manage reporting on and was excited to see that we could now do multiple contacts in our Assigned To column. However, when adding new projects with this feature enabled I noticed that Reports count those columns as different than other Assigned To columns without this