Hello,

We have recently begun working with Smartsheet and we detect that nonworking days are only greyed out when the setup gantt menu is openned. Is there a bug in our system or a configuration is needed? 

It occurs with a single new project without changing anything.

We have seen a similar

11

Hi all

 

I am currently compiling a project plan to manage various peices of work within my team. I have columns for start and end dates and a duration (in days) column. What this doesn't take into account are days that my team are out of the office (on annual leave, for example) and not working on