How I Use Smartsheet
Project Management during the design development of multifamily residential, and commercial projects.
I stop when construction starts, and in a monitor and control phase.

10

I have a number of milestones (0 duration lines) in my projects. These represent decisions, meetings, inspections and deliveries. I also use % complete to communicate with our finance department, customers and project team members. These factors don't seem to play well with each other in the

213

I am running a project where certain tasks are the responsibility of small project teams.

As the teams are flat in hierarchy I would like to assign tasks in my smartsheet to multiple (generally only 2 or 3) people, such that they receive reminders, update requests, notifications etc and can update