Hello, I recently ran a global update on a dashboard in a child blueprint and found all existing projects now show a "missing data" in a metric widget. New provisioned projects do not have this issue. The metric is pulled from a sheet cell that is part of the project blueprint. The source sheet has not been renamed or…
Have discovered that column description additions or changes is not possible through Global Update. In order to change a column description now, I have to rename and hide that column (since you also can't delete a column through global update) and then add the column back in again with the desired column description.…
This discussion has been merged.
We have one blueprint has over 370 projects and after 2 years in, our process changed and I need to add Summary row to one of the sheet. Currently we are unable to do this with Global update since Summary row did not existed before in this particular sheet.
Add a global update to update project plans with new rows and comments within Control Center so that all plans have the necessary steps needed for full implementations.
You should be able to use a global update more than once in Control Center, essentially setting up a template like you can with, for example, Data Shuttle. Many of my global updates will be the same one or two actions, like updating a column formula in my template, performed multiple times over time. It's cleaner and more…
I'm working on a global update where I want to add a column to reflect the project name so all the automations include the correct project reference. We use a template that is consistent for every (new) project created. My goal is to add this new column to the overall admin template so both existing and future projects…