I want to automatically assign our year quarters to a date range so the formula would select Q1 IF date created is between A/B Q2 if date created is between C/D etc - I have no idea where to start can anyone help?
Hi Team - I have a bit of a doozy.. at least it is for me. I have a sheet that needs a status populated considering 2 different date columns. If either "Expiry Date" or "Expiry Date 2" is in the past we need a "Red" status If either "Expiry Date" or "Expiry Date 2" columns are within the next 30 days "Yellow" Status If…
I am not sure how to "Nest" if functions for my application or if I need to use the "AND / OR" functions with it. Essentially, when my field team updates the [Field Status] column I want the appropriate colored circle to update in the [Risk Status] column. Red = Delayed Gray = Not Started Yellow = In Progress Green =…
I am trying to get a value when I put in a particular date If a person puts a date in the Target completion field, I want to return a Sprint in the Sprint field. I dont know if I can use the month or does it have to be between? For example =IF([Target Completion Date]@row) is between 8/1/2024 and 8/31/2024 then return…
=IF([Total Score]@row >= 3, OR [Impact]@row= yes, OR [Visibility]@row = yes, "Submit", "No") Struggling with this formula in my risk assessment column formula. The Total Score is equal to or greater than 3, or Impact is Yes or Visibility is Yes
Hi! I am a SS newbie and can't figure out what is probably a very simple formula. I am needing my Project Status to change to "Design" when the ALTA Survey Completion is checked actual and/or when the As Built Received Actual is Checked.
I can get both of these to work separately, but when I try combining them, using IF(OR or IF(AND or even just another IF(, the "Yellow" part won't work. Suggestions, please? =IF([Milestone Due Date]@row > ([Today Helper]@row + 30), "Green", IF([Milestone Due Date]@row > ([Today Helper]@row + 7), "Yellow", "Red"))…