Hello, I'm in the process of converting an excel spreadsheet into a smartsheet, but I've run into a problem. I'm trying to split 80% of a cost over a duration and then take a two month break before sh…
Hi, I'm in the process of transferring a spreadsheet into smartsheet that splits costs by months, and I've ran into a #DATE EXPECTED error for my formula. I can't change the column type as the formula…