Re: Smartsheet Jira Connector - Update Based on Smartsheet Column?
I did find a way to do this (although it's a bit of a process and prone to breaking). I have all tasks that are in the Filtered out by Connector - not synced sub-tasks being copied to another sheet. …1 · -
Re: Formula for Join, Collect, and If Statement - Resources Availability
@Paul Newcome I think I got it! =JOIN(COLLECT({Resources}, {Collect Info}, (CONTAINS([FY W Start]@row, @cell)), {Function}, Function@row), ", ") . I'm not sure if there is any major differe…1 · -
Re: Start Dates Are Earlier than Target Dates
Yes, thank you!1 · -
Re: Automatic Cell Linking From Blueprint Template
No problem. I actually got it to work. I have the rows from the project copied over to the sheet and then have datamesh doing the work to keep it updated from the report. Thank you for the idea - it'…1 ·