Re: Project Schedule Health from PMO Template
Hi @Marcia562, Here is a revised version that will have activities that start in the next 10 days turn green: =IF([% Complete]@row = 1, "Blue", IF([End Date]@row < TODAY(), "Red&quo…1 · -
Network Diagram (Process Flow) View for Sheets
Develop a new view for Sheets that displays connected tasks as a network or process flow diagram. Once you have identified the activities and their dependencies, you can visualize the critical path a…9 · -
Free Float [Slack] Formula
Calculate the float (or slack) between the task and the next successor task. If there are multiple successors, then it will select the one with the closest start date. Free Float (FF): The amount of …11 · -
Option to remove zeros from Scatter Charts
When using a scatter chart any value of 0 is plotted on the axis. It would be great to have an option to toggle off displaying these values. It crowds the scatter plot with junk information. Here is …6 ·