HI all,
I am new to smartsheets and is setting up my first project plan.
I have task A and Task B
Task B is depending on Task a finishing
so I have added a finish start depency of task A to task B - Great.
but now I realize I forgot Task C which must start after task A finishes but End before task B starts.
so I added a finish start dependency to task A
and a start finish depencency to task B
Expecting smartsheets moving task B into the future after task C finishes.
But no - it just adds some odd arrows between task B and C not updating the timeline in my Gant chat.
is this a bug?