I built one of our first project plans yesterday after getting a working template set up. However, the %age complete on the project is very wrong.
Here's how it's made up
- Initiation - 5 tasks in Initiation. All complete. Approximately 15 hours of effort.
- Definition - 20 tasks broken down into 5 subtasks. Its 95% complete. Approximately 100 hours of effort.
- Implementation - 150 tasks. None complete. Approximately 400 hours worth of effort.
- Cutover & Launch - 12 tasks. None Complete. Approximately 50 hours worth of effort.
- Handover & Closure - 5 tasks. None Complete. 4 hours worth of effort.
How does it calculate that my project is 61% complete?
More importantly, what can I do to get an actual figure which takes into account the actual effort required? It feels like the product is missing key tools like this.