My project team work on Saturday then next week we are off on Saturday. That cycle keeps going like that. How can I describe that and update in calendar in smartsheet? Thank you!
If I understand you, you mean that you team work Alternate Saturdays?
In the Project Settings set Saturdays as working then enter Every other Saturday as non working. Not neat and simple but works.