Here is my set up:
- Datatable that contains all actual charges for our company's projects
- Project "actual charges" sheet that connects to this datatable and pulls in data based on a project ID
- Several other project sheets that link via formula to the project "actual charges" sheet
Prior to implementing the datatable, there was another sheet being used to get actual data into Smartsheet that was not a datatable, but another smartsheet grid that was connected via a Datashuttle/attachment upload to a sheet. All of the project worksheets that referenced the "actual charges" sheet worked just fine and quite well with data being pulled in and analyzed, then dispersed into dashboards.
After now connecting the project "actual charges" sheet to a Datatable (via add and update mode), none of the formulas are working. All the data flows into the project "actual charges" sheet as intended but the formula processing now across the project-specific files seems broken. I am at a loss for what I did wrong, or if there is just an extreme lag on Smartsheet with formulas processing through all of the linkages? Any help would be greatly appreciated.