I want to create an if statement in my % complete column such that % complete goes to 100% when another column has a date.
Try (Change Due Date to your column name):
=IF(ISDATE([Due Date]@row), 1, 0)
Thanks! It works if I eliminate any dependency for the %change column.
Hey, Is anyone else facing this issue in the approval notifications sent through smartsheet
I have a sheet with a list of customers in one column, and then the following columns are City, Monday, Tuesday, Wednesday, Thursday, Friday. I need help with a formula that I can put in my sheet summary so that if the customer column says Staples (It can say this in multiple rows) that it will tell me the total package…
Hi Smartsheet community, I've always tried to answer questions but this is my first time posting. So I have formula =IF([Project Status]@row = "Complete", 1, 0) set up in the "Complete Check - Hide column" to check the box when the project status is marked complete. The project status column is tied to several other sheets…