-
Week over Week Variance?
Hey Smartsheet Friends! We are operating in a Construction Environment where we are tracking an entire build schedule, start to finish. At the beginning of the project, we set the baseline to track the original start and original finish date. This allows us to understand the length of time that we deviated from schedule…
-
Baselines for New Tasks
I use the baseline feature with the GUI extensively in my projects. During project execution, I frequently am adding/removing tasks to reflect the maturing scope of work. This means that unless I rebaseline the entire project (and lose historical projections in the process), these newly added rows go without baseline data.…
-
How to display baseline summary data on a dashboard
On a project rollup dashboard, Ideally I would like to display alongside each projects baseline data of Baseline Start/End dates, and variance. I would like to show the date/time and user who reset the baseline. Tried a few different ways but cant seem to capture this data into either the sheet summary area or a project…
-
Choosing Column for Baseline
I have a sheet that has three existing date fields. I want to create a baseline on two of the fields. When I set up a baseline it uses the wrong field for completion baseline. I can't seem to figure out how to change what columns it uses.
-
Is there a way to pull the baseline start & end dates from a project sheet?
I am creating a project status dashboard that will encompass all of our projects. It's simple enough to link each line to a project but the thing I want to be able to grab is the baseline start and end dates from the project. Short of scanning a column and finding the lowest and highest numbers, is there a way to access…
-
Baseline
Hi: I have a sheet with parent and child rows. When I select the baseline, the sheet gives me the baseline of the whole project, not from each process(parent row). There is a way to see the baseline of each parent rows with his childs?
-
Baselines - Variation Field in Business Days?
Really happy to see this baseline feature in Smartsheet and have been using it effectively. There is one item that doesn't quite seem to make sense with other smartsheet behavior for me. The Variance shown is in absolute days between two dates - I understand a logic for that, however given the duration column is processed…