Is there a way to proactively include the three baseline columns in blueprint within Control Center?
The challenge I'm facing is that these columns aren’t created until the baseline is saved on the sheet—after it's already provisioned via SCC. I’d like to add them to the blueprint template sheet ahead of time so they can be incorporated into my profile data and made available for reporting. How can I do that?
-
I would like to use the baseline function within a gantt view but only rebaseline select row(s).
I would like to use the baseline function within a gantt view but only rebaseline select row(s). I use one Smartsheet for many projects, but only one of them needs a baseline at this time.
-
Formula using project plan Baseline columns that may not yet exist as Baseline hasn't been set
I would like to put a formula in place for the health of milestones within project plans deployed as templates in a Control Center blueprint. The formula would work similarly to how it works in the Project Plan template provided in the Project Management Office template set available in Smartsheet. However, the template…
-
Baseline disappearing when exported in PDF/PNG.
I've discovered a bug where the baselines displayed on the Gantt chart disappear when exported to PDF or PNG. This is clearly a defect, and I hope for a swift fix.
-
Adding New Task After Setting Baseline
Smartsheet Community: Once The Baseline is Set. It Would Be Nice to Have The Ability to Add New Tasks and for those Tasks to be Added to The Baseline without Re-Setting it. Today, I have to Manual Change All the Dates. This Drastically Increase human Errors and is Very Time Consuming.
-
Merged: Baseline selected rows
This discussion has been merged.
-
Formula help on RYG Balls for Baseline Variance
hello all I'm struggling with this because the variance is in Days. I did a basic IF statement where: if the Status = complete then Green, and "nested if" if the Variance was < -5 then Red else Yellow. It just turned complete things Green and everything else yellow, because the variance is in Days (eg. 1d or -2d not a read…
-
One template with scroll down options for different timings of tasks
Dears, As we know making formulas in duration time is not possible, so I'm looking for other option to make life easy in below scenario: We have several production plants, producing different product types and using different packaging pritnters which has influence on overall project timing for new product introduciton. I…
-
More than one Baseline + Comments
Dear all, To enhance Smartsheet as a comprehensive PM Application, my company and I find that a crucial feature, baseline management, currently needs to be added. While the ability to set baselines is valuable, the limitation of only being able to set one baseline is a constraint. We propose the implementation of a feature…