Choosing Column for Baseline
jevans
✭
I have a sheet that has three existing date fields. I want to create a baseline on two of the fields. When I set up a baseline it uses the wrong field for completion baseline. I can't seem to figure out how to change what columns it uses.
Tags:
Answers
-
I figured it out. This is under Project properties. Note you can not use a column that has a formula in any of the cells, but you can add formulas to the cell after the fact and it will work as long as those formulas are producing a date.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives