Choosing Column for Baseline
![jevans](https://us.v-cdn.net/6031209/uploads/defaultavatar/nWRMFRX6I99I6.jpg)
jevans
✭
I have a sheet that has three existing date fields. I want to create a baseline on two of the fields. When I set up a baseline it uses the wrong field for completion baseline. I can't seem to figure out how to change what columns it uses.
Tags:
Answers
-
I figured it out. This is under Project properties. Note you can not use a column that has a formula in any of the cells, but you can add formulas to the cell after the fact and it will work as long as those formulas are producing a date.