-
How to get project overall delay in days in Smartsheet
Hi While we use the Baselines on the task level to see the delays per task, is there a way to grab the overall project delay in days and also show it in the Dashboard? Thanks for any prompt Regards /Marat
-
Using Smartsheet Baselines values
Is there a way to use a helper Column and Formula to turn a Smartsheet Baseline variance into a real number so I can get an average? OR is there a better way to baseline changes to end dates?
-
Baseline Duration and Predecessors
I'd like to create a column for Baseline Duration and Baseline Predecessors, along with the current Start and Finish Date columns, when I baseline a schedule. In the cases where new tasks are added/inserted, the baseline predecessors would have to automatically adjust for the new row number that the predecessor has now…
-
Undo Baseline
The feature to undo a baseline that was recently executed in error would be really helpful
-
Reset Baseline Not Appearing for Admin Users
We're having an issue where the Set/Reset Baseline buttons are not appearing for Admin users. Is this a known issue or is there a setting we need to change so these appear in the baselines popup? Thank you! Note: We have tested multiple browsers for this. Users with a license can see and use the baseline set/reset buttons,…
-
Formula using project plan Baseline columns that may not yet exist as Baseline hasn't been set
I would like to put a formula in place for the health of milestones within project plans deployed as templates in a Control Center blueprint. The formula would work similarly to how it works in the Project Plan template provided in the Project Management Office template set available in Smartsheet. However, the template…
-
Baseline Visual in Gantt or Timeline view?
Hello! We have baselines set up on our sheet. Is there a way to show the variance visually, in the Gantt or new Timeline view - or is it only visible in that column as a number? Thanks!
-
Merged: Baseline Date Functionality
This discussion has been merged.
-
Keeping track of old baselines
Hi I want to know if there is a simple way of keeping a log of baselines, e.g. each time it is reset, the old baseline is logged, similar to version control. The idea is that at the end of a project (which underwent change control resulting in the timeline needing to be re-baselined) we will be able to review the changes…
-
Baseline new activities added to schedule
How do I baseline new activities added to my schedule without it impacting the baselines already established for activities that had been in the schedule? My schedule is being populated in phases so new activities will be added over time. If I reset the baselines already established for work that was in the plan already,…