Target Date vs Baseline in Project Management Office template
The project plan in PMO template have Target Start Date and Target End Date which seem to serve the same purpose as the Baseline Start and Baseline Finish. Are they redundant or am i missing something?
-
Baseline Visual in Gantt or Timeline view?
Hello! We have baselines set up on our sheet. Is there a way to show the variance visually, in the Gantt or new Timeline view - or is it only visible in that column as a number? Thanks!
-
Merged: Baseline Date Functionality
This discussion has been merged.
-
Keeping track of old baselines
Hi I want to know if there is a simple way of keeping a log of baselines, e.g. each time it is reset, the old baseline is logged, similar to version control. The idea is that at the end of a project (which underwent change control resulting in the timeline needing to be re-baselined) we will be able to review the changes…
-
Baseline new activities added to schedule
How do I baseline new activities added to my schedule without it impacting the baselines already established for activities that had been in the schedule? My schedule is being populated in phases so new activities will be added over time. If I reset the baselines already established for work that was in the plan already,…
-
Easily Set Baselines in WorkApps
In the current state, we cannot set baselines from WorkApps unless we set the desktop view to grid view. This is not an ideal experience. Don't really want the project schedule in Gantt view at all times. This may spark the need for a second enhancement request related to being able to switch views in WorkApps, which…
-
Auto set Baselines
Is there a way to configure smartsheet to automatically set baselines at certain milestones in a project? My thought with this is my project plan would automatically set a new baseline at 3 different milestones, I would end up with 3 sets of baseline date columns. This would easily allow me to go back on projects and see…
-
Record Baseline Date in Activity Log
I oftentimes need to know on what date I baselined my project schedule in Smartsheet, but the date doesn't seem to be recorded anywhere. It would be nice if either the Activity Log or Baseline window showed the date when the schedule was baelined.
-
Insert todays date on a project plan start date column
Hi, I use blueprint control center to replicate the templated project plan for every project that we approve. I want to automate the start of this project plan by entering the date it was created as the initial starting date for the first task. My plan is full of predecessors, so once the initial date is inserted in the…
-
More than one Baseline + Comments
Dear all, To enhance Smartsheet as a comprehensive PM Application, my company and I find that a crucial feature, baseline management, currently needs to be added. While the ability to set baselines is valuable, the limitation of only being able to set one baseline is a constraint. We propose the implementation of a feature…