-
Using IFS statement with date and check box
The simple statement is I want to have a sum of work hours in a department, that is still incomplete, during a calendar period. Currently the formula is: =SUMIFS([Work Hours]:[Work Hours], Department:Department, "Wire", Finish:Finish, >=DATE(2020, 9, 1), Finish:Finish, <=DATE(2020, 9, 30)) * 8 A suggested version has been…
-
Duration to a specific task from project start / counting the number of project days
Hello, I'm wondering if there is a function in Smartsheet by which I can create a column that displays the total number of project days from the beginning of the project ("Project Day 1") up to the beginning of each task. For example, the first task would start on "project day 1," the last task of the project would start…
-
Tracking % Changes Over Time
I have a master sheet (linked to many other, scope-specific QC sheets) that calculates % completion per task. Each row is for a different task, and each task has their own amount of steps. This information is all linked & calculated from the scope-specific sheets. Column 1 shows "# of steps completed to date", column 2…
-
Auto fill cell value if adjacent cell matches cell in another sheet.
Hello, I am working on a construction project with a lot of RFIs and would like our issue tracking logs to reference my main RFI log. All the RFIs have unique ID #s. I want the Issue tracking logs to update the RFI # once it is updated on my main RFI Log. my main log: 1st column is RFI #, and 2nd column is internal…
-
Quality Control Record
Hi, I am trying to create a smartsheet to track the quality of a constructed panel. The constructed panel needs to be checked at certain points by different team members. The data needs to be stored to each individual panel. I have tried using forms to submit the data onto a sheet however if i want to add multiple columns…
-
Renaming Workspaces
Is there a way for admins on workspaces to be able to rename them, or is it only workspace or sheet owners that can do this? Since the admin has full sharing/editing rights, it would be helpful to have them be able to do everything the owner can do so there isn't a bottleneck with every change having to go through the…
-
Web Form Update Multiple Sheets
Hello, I need help figuring out how to have a web form update multiple sheets based upon location information. Basically I have put together a web form that will do a site survey of hotel rooms for renovation. We are surveying several sites at a time and instead of creating 20 different web forms that update 20 different…
-
Gantt - Progress Ahead or Behind Schedule?
Hi All I'm keen to look into options to report on project progress against schedule. Generally we set a project programme, then progressively update %Complete against lines and the project progresses. The progress bar works well as visually indicating if each activity is ahead or behind the current date. I'm looking to try…
-
Form Submission
If I create a form in smartsheet and someone were to complete the form, can I make it so that multiple people can be notified about the form submission and have access to the information submitted? If so, how do I do that? Can this be done automatically without me having to check daily and send notification via email…
-
Copy folder error
I have created a folder containing 15 sheets with various links to reference sheets (outside of this folder) and datameshing. The idea is that I can copy the folder, change a cell reference (location) and the new folder will update with the reference data for that location. I've "saved as new" the folder and gotten an…