Alerts/Notifications based on cell color
I would like to create an alert. If a cell turns red in a delivery date column, email PM assigned to PM column and another editor within the sheet. Do not see how to establish an alert just based on change of color.
-
Formatting with alerts
I need to do the combination of formatting with and alert, but seem to have hit a wall. If column "delivery type"= selection "o" and column "1st delivery" has a date that is past due then turn "1st delivery" to red and send an alert to the contact in columns "PM" and a particular individual. Any help would be appreciated.
-
One Task with multiple Predecessors
Hello, New to SmartSheet. Question is, I am working backwards, and i have one Task (Task 3) with four Predecessors. These four Predecessors end up having different Start dates. Task 3 ends up having an End date of the Predecessor with the shortest Duration. Shouldn't Task 3 have an End date of the Predecessor with the…
-
Update Request for Specific User
I have a large project sheet with multiple people assigned to various tasks. I want to send out a weekly update request, but don't want to have to select each row for each different user, as these change as a project moves along. I have several people outside my organization where update requests work perfect for them…
-
Auto numbering each line
1. Is it possible to assign the values of the number in each new line with a given step (or digit number) For example: 005 010 015 020 025 etc. 2. If I need to insert a new line between 010 and 015, I would like to be able to recalculate all subsequent rows in accordance with clause 1. And the second option is to set the…
-
Submitting Product Enhancement Requests
I understand that by submitting a "Product Enhancement Request" it doesn't mean it will be actioned and even if it is, will materialize in the immediate future. I think that rather than it them seemingly disappear down a 'black hole' a published list and the status of requests would be useful.
-
Conditional formatting if task is behind schedule
Hi guys, I'm new to Smartsheet so forgive me to ask the question. How do I setup conditional formatting to a task that is behind schedule? I created 2 lines of conditional formatting already: 1 ) task is 100% complete -> green row 2) end date is in the past and % complete is not 100% -> red row I'd like to add a third…
-
Smartsheet Experts
Hello I have been supporting a company in implementing Smartsheet. Successfully :) Today, I'm getting more and more involved in various other important projects and as a result need extra competent workforce to help me supporting our teams. Any interest? Raoul.
-
#Circular Reference when automating Yes,Hold,No decisions
Hi, Hit a lil road block here. Trying to automate the symbols for my status column based on drop down lists, but i keep getting a circular reference when putting in this formula, =IF([Lead Result]1="Win",Status1="Yes",IF([Lead Result]1,="Negotiating",Status1="Hold",Status1="No")) Posting a screenshot of my sheet for…
-
Formulas: Countif / And / Children Rows
H E L P! What is a simple way to formulate the "Evaluation" Chart in the Screen Shots attached, based off ONLY the children rows of the 4 Departments on the top of the sheet in both the "status" and "risk level" columns? I'm trying to avoid a "messy" formula but I'm receiving an error through all my attempts.