-
Include predecessors in Filter creation
I would love to add the option to include predecessors/dependencies in my filter option (just like the ability to include parent rows - like a little checkbox). This will allow me/my business the opportunity to see what feeds the tasks they are filtering on to see if there is any analysis that can be done to help mitigate…
-
Merged: Add elapsed days in predecessor column
This discussion has been merged.
-
Enhanced predecessor cell editing for dependency management in table view
September 16, 2025 We recently expanded dependency management in table view. In addition to editing task start and end dates, users can now define and manage predecessors directly in the sheet, making it easier to keep project schedules accurate and aligned. Predecessors let you link tasks so that dependent dates…
-
Duration vs predecessors, for parallel activities (not auto updating on gantt chart)
based in the example below, I have various assignment and activities that run parallel to various construction activities across construction stage. How do i set smart sheet to prioritise predecessor? Research: this behaviour is a known limitation in Smartsheet. Unlike MS Project or Primavera, Smartsheet does not…
-
Manually Adjust dates with Predecessors
I am new to smartsheets (as is my team), and so far we have been found smartsheets as an acceptable software solution. However, I recently discovered that I am unable to manually adjust dates if there is a predecessor. this functionality is a requirement. an non-negotiable (for me) requirement. Here is an example: I have…
-
Listing dependencies by action number
I am currently maintaining an action/deliverables register with approximately 500 line items. Each line item has a corresponding unique action ID code (e.g. AE11.02.01), which contains useful information regarding the relevant business area and related topic. Currently any dependencies are listed by row number and is only…
-
How do I use predecessors to ensure a portion of rows are complete before being able to go to the ne
I am wanting to use this format for pre-con to ensure nothing is missed or overlooked. I want to mitigate mistakes from our project managers to prevent project issues by not allowing them to move to the next section until the section they are working on is complete. We also want to use conditional formatting to have the…