Successor tasks have mysteriously changed to start the same day predecessor ends
While reviewing a timeline created several days ago I realized that successor tasks are suddenly starting the same day predecessor tasks are ending. For example, Task A ends on 4/10/26 and task B begins on 4/10/26. Previously, task B would begin the following day, in this case 4/13/26 because Saturday and Sunday are non…
-
Mysterious Date Changes... Dependencies and edays?
Hello, I've had a few users reach out to me today about seeing changes to their project plans, but no one went in to change dates. The activity log was clear of anyone specifically doing anything to affect the start and end dates. The recent user, after investigating her plan, had a predecessor (our dependency column) that…
-
Impossible to set a Date Constraint (Blue Anchor) - Predecessor is being deleted instead
Hello,I'm struggling with date constraints on child rows. Setup: Dependencies are Enabled. I have a standard Parent/Child hierarchy. I want a child row to have a Predecessor but also a "Start no earlier than" date (manual constraint). The Issue: Every time I manually enter a Start Date on a child row that already has a…
-
Is there a way to turn off these lines?
The gantt is looking too clutter for our liking. Is there a way to turn off the connectors lines to give a cleaner appearance for print outs?
-
Include predecessors in Filter creation
I would love to add the option to include predecessors/dependencies in my filter option (just like the ability to include parent rows - like a little checkbox). This will allow me/my business the opportunity to see what feeds the tasks they are filtering on to see if there is any analysis that can be done to help mitigate…
-
Enhanced predecessor cell editing for dependency management in table view
September 16, 2025 We recently expanded dependency management in table view. In addition to editing task start and end dates, users can now define and manage predecessors directly in the sheet, making it easier to keep project schedules accurate and aligned. Predecessors let you link tasks so that dependent dates…
-
Duration vs predecessors, for parallel activities (not auto updating on gantt chart)
based in the example below, I have various assignment and activities that run parallel to various construction activities across construction stage. How do i set smart sheet to prioritise predecessor? Research: this behaviour is a known limitation in Smartsheet. Unlike MS Project or Primavera, Smartsheet does not…
-
Manually Adjust dates with Predecessors
I am new to smartsheets (as is my team), and so far we have been found smartsheets as an acceptable software solution. However, I recently discovered that I am unable to manually adjust dates if there is a predecessor. this functionality is a requirement. an non-negotiable (for me) requirement. Here is an example: I have…
-
Merged: Add elapsed days in predecessor column
This discussion has been merged.
-
Listing dependencies by action number
I am currently maintaining an action/deliverables register with approximately 500 line items. Each line item has a corresponding unique action ID code (e.g. AE11.02.01), which contains useful information regarding the relevant business area and related topic. Currently any dependencies are listed by row number and is only…