Manually Adjust dates with Predecessors
I am new to smartsheets (as is my team), and so far we have been found smartsheets as an acceptable software solution. However, I recently discovered that I am unable to manually adjust dates if there is a predecessor. this functionality is a requirement. an non-negotiable (for me) requirement.
Here is an example: I have several tasks whose dates can be automated. However, one task must be manually scheduled. I need to be able to flip that task from auto to manually scheduled and have the gantt chart update appropriately. I also need a list that will tell me the reasons my start date is adjusting back if I change it.
In order to get around this, I have turned off predecessors and am now keeping the same project plan in MS Project so I can easily calculate dates. I am then wasting time transferring dates over to smartsheets. This is not an acceptable solution to this gap in your product's functionality.
Please fix this as soon as possible. This issue will rapidly drive me back to MS Project (as in I'll stop using it Monday at 8am rapid), I will also recommend to my organization that we NOT adopt smartsheets and I will advise against using smartsheets anywhere and everywhere I end up going - not out of pettiness, but because the software doesn't meet my needs as a project manager.
Please do not respond with "work arounds". I don't need work arounds I need functionality. Please fix this as soon as possible.