-
Rows will not stay in place. NEED HELP NOW
We use a sheet as both a schedule and data collection tool as part of a much larger system we just put in place (literally 5 days ago, moved from google sheets). The information is organized manually first by employee and second by the priority of projects. Recently, the information in the sheet began jumping randomly…
-
Ability for PM's to select which projects they want to receive a status update request e-mail
On an ad-hoc basis I need project managers to be able to select which project(s) they want to receive the status update request so they can update accordingly. Currently In my dashboard I give them access to a separate "project selection" sheet containing the project list (linked in from the master data sheet) and a…
-
Issues with alerts - not sending 'right away'
I created alerts to be sent 'right away'. However, we are receiving them via email several hours later - sometimes 12 hours later. I confirmed that I checked 'email' in my notification settings. Can you please help me figure out why there is a delay?
-
Calculate Reverse Date Format
Hi dears if someone can help with this format I have 3 cells: 1-ESTIMATED REQUIRED DELIVERY DATE: include the estimated date of delivery 2-PROCUREMENT TIMELINE: autogenerated including the number of working days 3-PR ESTIMATED SUBMISSION DATE: I need to create a formula that can automatically calculate the reverse date of…
-
Percent Formatting applied, but entry of 100 is shown as 10,000%
I have the entire column formatted as a percent, but when I enter 100, it shows as 10,000%, or when I enter 1 it shows 100%. Would like for the number entered to show that percent.
-
SUM of Only Parents in Budget Sheet
Hello! I've created a budget sheet with sub items. I figured out how to SUM the Children under a Parent line but what is the simplest way to SUM only the Parents for a Total that does not include both Children and Parents? Thank yo!
-
Is it possible to stop a flow pulling in a duplicate line item
Hi all, Hope you are all well! With the help of this community i have created a form that will automatically identify how a line item and how long it is before being cancelled. This form will then send emails to Project Managers once we are 5 days away from cancellation and then a day away. Because of this, we are going to…
-
Effort Vs Duration
Hi I am new to smartsheet and wondered if you could help. I would like to create a project plan which shows the effort required vs the duration. for example: a task may take 2 days to complete however they can complete this anytime within a 5 week time spell - how would I show this on the plan so that the resource…
-
Is there a way to pre-populate past survey responses by user?
I have a feedback survey(form) that users fill out a few times a week and I was wondering if there is a way to have their responses pre-load from the last time they answered. For example, say they fill out the survey three times a week and nothing has changed over the course of the week and they want to submit the same…
-
Aggregate Status Circles w/ Formula
Hi, I have these multiple statuses across 4 projects (each project is one of the rows) within 1 program and I want to be able to incorporate a formula where I can summarize all of these to a single row with the same columns in a separate sheet to present at the program level. Formula to say: If there's at least 1 yellow…