I would like to have Task D begin when Task A or Task B is completed. How can I set multiple predecessors?
Task Name | Start Date | End Date | Duration | Predecessor
Task A | 7/1/2021
Task B | 7/11/2021
Task C | Start Date should be 7/1 is Task A completes first or 7/11 if Task B completes first.
Tags:
Answers
-
There currently isn't a way to set multiple, conditional predecessors in Smartsheet. Please let our Product team know about your request and feedback by filling in this form, here!