I would like to have Task D begin when Task A or Task B is completed. How can I set multiple predecessors?
Task Name | Start Date | End Date | Duration | Predecessor
Task A | 7/1/2021
Task B | 7/11/2021
Task C | Start Date should be 7/1 is Task A completes first or 7/11 if Task B completes first.
Tags:
Answers
-
There currently isn't a way to set multiple, conditional predecessors in Smartsheet. Please let our Product team know about your request and feedback by filling in this form, here!
Thank you,
Genevieve
Join us at Smartsheet ENGAGE 2024 🎉
October 8 - 10, Seattle, WA | Register now
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.8K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!