Setting predecessors with multiple tasks

Options

I would like to have Task D begin when Task A or Task B is completed. How can I set multiple predecessors?

Task Name | Start Date | End Date | Duration | Predecessor

Task A | 7/1/2021

Task B | 7/11/2021

Task C | Start Date should be 7/1 is Task A completes first or 7/11 if Task B completes first.

Answers

Help Article Resources

Want to practice working with formulas directly in Smartsheet?

Check out the Formula Handbook template!