Setting predecessors with multiple tasks
I would like to have Task D begin when Task A or Task B is completed. How can I set multiple predecessors?
Task Name | Start Date | End Date | Duration | Predecessor
Task A | 7/1/2021
Task B | 7/11/2021
Task C | Start Date should be 7/1 is Task A completes first or 7/11 if Task B completes first.
Tags:
Answers
-
There currently isn't a way to set multiple, conditional predecessors in Smartsheet. Please let our Product team know about your request and feedback by filling in this form, here!
Thank you,
Genevieve
Join us for Jumpstart 2025 with Community on 23 January (in two time zones)! 🎉 Register here.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 65.1K Get Help
- 444 Global Discussions
- 142 Industry Talk
- 472 Announcements
- 5K Ideas & Feature Requests
- 83 Brandfolder
- 150 Just for fun
- 71 Community Job Board
- 489 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 301 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!