I imported a project from MS Project with WBS. How can I maintain the WBS numbering when adding/deleting tasks?
Hello,
Any WBS numbering will need to be manually adjusted as needed when tasks are deleted, as Smartsheet currently doesn't have automatic WBS numbering.
When you have a moment, submit a Product Enhancement Request using the form under Quick links on the right and let our Product team know that you'd like WBS auto-numbering in Smartsheet.