Hello !
Does anybody know if how to show on the same line of the Gantt mode, the expected planning and the reality.
Here attached is an example of what I need.
Thank you for your help !
Hi,
Unfortunately, it's not possible at the moment, but it's a great idea!
Please submit an Enhancement Request when you have a moment.
There are third-party services that work with Smartsheet that could help. Is that an option?
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
Hey
We are using Baseline start and finish dates. The following link might be very helpful to you:
https://www.smartsheet.com/blog/smartsheet-tips-tracking-baseline-schedule-variance?_ga=2.233988571.452105373.1556563149-2037575016.1556563149
I hope this helps you.
Kind regards,
Jana
I generally track the Projected vs Actual using a chart on a dashboard.
Hi, We are a developer and building a custom web platform for one of our client who is using smartsheet. Our platform needs to get data from smartsheet and need to show the data in our custom UI. Could anyone recommend the APIs we should be using for this?
This solution updates a column formula across multiple sheets in a workspace. The script finds all sheets with a certain string in the name, finds a certain column by name on those sheets, and then updates all column formulas to a new column formula. At the time of posting, Control Center Global Updates did not allow me to…
We have a webhook created in one of our Smartsheets, and we've been noticing lately that the webhook callbacks immediately disables the webhook after 1 try, causing data discrepancies between the Smartsheet and the system it sends the data to. Here's an excerpt JSON message received from Smartsheet showing the callback…