Hi all,
I would like to create a workflow to send out reminders to assigned persons of tasks (cards) 3 days before the task is due. I set-up the attached workflow but at the moment it's sending reminders on the exact due date and not 3 days before. Would be happy to get your advise. Thanks so much! I'm using smart sheet card view.
Christina
Question. Are you trying to trigger these responses yourself? If so you'll need to navigate to Account Dropdown > Personal Settings > Notifications and make sure that the checkbox for include changes I make is checked.
See screenshot.
Click on where it says "Run Once" then select "Custom". You can then set it to repeat every day and have your condition of when the Due Date is in the next 3 days.
Doh. I completely missed the part where you said it was launching on the due date.
(-‸ლ) OY.
Alternatively (sorry - late to the post here and you've probably found it already) in the workflow dialog box instead of saying "Run once" "on" change ON to "3 days before" and select your Due Date field. Then it will send the alert just once, 3 days before the due date. This method doesn't need the current criteria of date due in the next 3 days; but I would add a criteria condition to state that the status of the Task is NOT Complete, as if the task is already complete you don't need the reminder!
So many ways!
Kind regards
Debbie
Jippie, thanks so much for your help Paul, working!
Haha no worries Mike, thanks anyways!
Happy to help!
Debbie, I really love your suggestion!
I tried to set it up (see screenshot) but somehow it's not working yet. May I ask for your advice again?
Thanks so much!
Hi Christina
The logic looks sound to me in the workflow.
Have you checked the little COG in the top right corner of the workflow manager. Do you have the permissions set correctly?
I usually set the permissions to the least restrictive.
The other reason why it might not work is if you are testing it with you as the assigned to email address, and in personal settings you have the restriction set up to NOT notify you if you are the addressee then this would also make the workflow not work.
Check these two things out then come back to me if still not working.
(I assume the status on the record is NOT Done or Stored!?)
Good luck!
Debbie! Thanks you so so so much and pls apologise my super late reply. It is working, so happy. Thank you so much for your advice, so cool
Take care
Glad you got things working as you needed them too!
Is there a way to revert to the old dashboard look and feel. The new dashboards do not look good at all. There is no way of knowing if there are additional items in the widgets until you scroll over one to learn there is more to it since the vertical bar doesn't show. We have hundreds of dashboards and they will all need…
When i try to send or print the timeline view instead of showing the progression bars like they do on the screen it only send the data entered and not a graph type view to print. Is there a way to do this. I am using a mac platform if that helps.
I have reproduced the following behavior in a validated Smartsheet application. User permission: Editor (not Admin) Row status: Locked (confirmed via row menu displaying "Unlock Row") Text, Date, Contact List, and Checkbox columns cannot be modified. Dropdown List columns remain editable. Selecting a new dropdown value and…