Hi,
after the project was created some columns were not correctly set, is there any way to ask contorl center to rebuild the reporting sheet ?
Hi Etienne,
There's a feature called Global Updates that is built just for this!
For sheets- https://help.smartsheet.com/articles/2476706-smartsheet-control-center-make-global-updates
For reports- https://help.smartsheet.com/articles/2479386-smartsheet-control-center-global-updates-reports
For dashboards- https://help.smartsheet.com/articles/2479391-control-center-global-updates-dashboards
I created an extensive automation to gather approvals on a change request. In the customized message I am referencing some fields. Some fields are dropdowns and other s are just contacts. However, when the message comes through, those fields are not populating any information. I have looked at my column names and they…
Hi everyone! I was wondering if anyone knows a way to attach a file upload space to an update request. I have already set up a workflow to send out a update request at the appropriate time but I cannot find a way to add an upload space. I know that I can add attachment when I manually send update requests, but I was…
Good afternoon, The current account holder is no longer employed with Ambipar. We need to have the primary account contact and ownership transferred from that individual to me. Could you please provide the contact information for a Smartsheet representative who can assist with this transition, or advise on the process…