Control Center Multi-Tier Auto-Provision
I'm looking to automate the provisioning of multi-tier projects in Control Center, but I wasn't sure how to pick the parent project for a particular provision. Is it even possible?
Answers
-
Yes you need to reach out to SmartSheet to turn this on. I have tried to do it on my own in a sandbox account to a config file and it doesn’t activate it on its own. I talked to my customer success manager and was told you have to request it to be turned on. Kinda like the increasing of linked cells when using SSC
Joe Goetschel | Smartsheet Director | SCS CLOUD - Smartsheet Partner
"The only real limitation of Smartsheet is the level of effort required to achieve your goal."
-
I have the feature turned on, I'm just trying to figure out how to auto-provision child blueprints in a manner that auto-assigns them to a parent based on intake info.
-
Got it! So I have 2 intakes. 1 for Parents and another for Children. There are some checks and balances on my intakes but the child blueprint has a radio button on the first page that says "Linked to a parent project".
Joe Goetschel | Smartsheet Director | SCS CLOUD - Smartsheet Partner
"The only real limitation of Smartsheet is the level of effort required to achieve your goal."