HELLO;

I HOPE YOU CAN HELP ME WITH THIS PROBLEM:

I NEED TO SCRATCH A FORMULA TO GENERATE DEPENDENCIES AUTOMATICALLY IN A PROJECT SHEET WITH THOUSANDS OF ROWS.

EACH ROW CORRESPONDS TO A TASK REPEATED RANDOMLY. AND MY PROJECT HAS MORE THAN 70 DIFFERENT TASKS, SO IT IS VERY LABORIOUS TO ASSIGN DEPENDENCIES USING FILTERS BY TASK.

ATTACHED THE LINK OF MY SHEET EXAMPLE IN WHICH I HAVE TRIED TO SOLUTION IT USING THE FUNCTIONS:

LOOKUP + MATCH

INDEX + MATCH

THANKS IN ADVANCE

http://publish.smartsheet.com/fb9df41f04754198b5e93de66eef8b54

<IFRAME WIDTH=1000 HEIGHT=700 FRAMEBORDER=0 SRC="http://publish.smartsheet.com/fb9df41f04754198b5e93de66eef8b54"></IFRAME>

DEPENDENCE.jpg

Comments

  • J. Craig Williams
    J. Craig Williams ✭✭✭✭✭✭

    question: task repeated randomly?

    I had a similar problem as one time, I believe. 

    Each project has a set structure of 5-10 tasks, all linked together, with modules of a fixed number that was determined on contract award. Depending on decisions made at project launch, the order was determined. Based on that info, the project was created using a script (outside of Smartsheet) and implemented in Smartsheet in less than an hour.

    It took a few days to design, implement, and test the script, but it worked and saved dozens of hours on each new project.

    Well worth the cost.