Month or "2023"

Hello

Hoping to edit this formula.

Currently shows month based on date entered which is perfect. But I wanted to add additional context for those dates not yet defined. So if "blank" to say this "2023 pending"

Thank you in advance

FORMULA:

=IFERROR(IF(MONTH([Project Start Date]@row) = 1, "January", IF(MONTH([Project Start Date]@row) = 2, "February", IF(MONTH([Project Start Date]@row) = 3, "March", IF(MONTH([Project Start Date]@row) = 4, "April", IF(MONTH([Project Start Date]@row) = 5, "May", IF(MONTH([Project Start Date]@row) = 6, "June", IF(MONTH([Project Start Date]@row) = 7, "July", IF(MONTH([Project Start Date]@row) = 8, "August", IF(MONTH([Project Start Date]@row) = 9, "September", IF(MONTH([Project Start Date]@row) = 10, "October", IF(MONTH([Project Start Date]@row) = 11, "November", IF(MONTH([Project Start Date]@row) = 12, "December")))))))))))) + " " + YEAR([Project Start Date]@row), "")

Best Answer

  • Andrée Starå
    Andrée Starå ✭✭✭✭✭✭
    Answer ✓

    Hi @Morris R

    I hope you're well and safe!

    Try something like this.

    =IF([Project Start Date]@row = "", "2023 Pending", IFERROR(IF(MONTH([Project Start Date]@row) = 1, "January", IF(MONTH([Project Start Date]@row) = 2, "February", IF(MONTH([Project Start Date]@row) = 3, "March", IF(MONTH([Project Start Date]@row) = 4, "April", IF(MONTH([Project Start Date]@row) = 5, "May", IF(MONTH([Project Start Date]@row) = 6, "June", IF(MONTH([Project Start Date]@row) = 7, "July", IF(MONTH([Project Start Date]@row) = 8, "August", IF(MONTH([Project Start Date]@row) = 9, "September", IF(MONTH([Project Start Date]@row) = 10, "October", IF(MONTH([Project Start Date]@row) = 11, "November", IF(MONTH([Project Start Date]@row) = 12, "December")))))))))))) + " " + YEAR([Project Start Date]@row), ""))

    Did that work/help?

    I hope that helps!

    Be safe, and have a fantastic week!

    Best,

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!

    SMARTSHEET EXPERT CONSULTANT & PARTNER

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35

    Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.

Answers

  • Andrée Starå
    Andrée Starå ✭✭✭✭✭✭
    Answer ✓

    Hi @Morris R

    I hope you're well and safe!

    Try something like this.

    =IF([Project Start Date]@row = "", "2023 Pending", IFERROR(IF(MONTH([Project Start Date]@row) = 1, "January", IF(MONTH([Project Start Date]@row) = 2, "February", IF(MONTH([Project Start Date]@row) = 3, "March", IF(MONTH([Project Start Date]@row) = 4, "April", IF(MONTH([Project Start Date]@row) = 5, "May", IF(MONTH([Project Start Date]@row) = 6, "June", IF(MONTH([Project Start Date]@row) = 7, "July", IF(MONTH([Project Start Date]@row) = 8, "August", IF(MONTH([Project Start Date]@row) = 9, "September", IF(MONTH([Project Start Date]@row) = 10, "October", IF(MONTH([Project Start Date]@row) = 11, "November", IF(MONTH([Project Start Date]@row) = 12, "December")))))))))))) + " " + YEAR([Project Start Date]@row), ""))

    Did that work/help?

    I hope that helps!

    Be safe, and have a fantastic week!

    Best,

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    Did my post(s) help or answer your question or solve your problem? Please support the Community by marking it Insightful/Vote Up, Awesome, or/and as the accepted answer. It will make it easier for others to find a solution or help to answer!

    SMARTSHEET EXPERT CONSULTANT & PARTNER

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35

    Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.

  • Frank S.
    Frank S. ✭✭✭✭✭✭

    Greetings @Morris R,

    Give this a try:

    =IFERROR(IF(ISBLANK([Project Start Date]@row), "Pending", IF(MONTH([Project Start Date]@row) = 1, "January", IF(MONTH([Project Start Date]@row) = 2, "February", IF(MONTH([Project Start Date]@row) = 3, "March", IF(MONTH([Project Start Date]@row) = 4, "April", IF(MONTH([Project Start Date]@row) = 5, "May", IF(MONTH([Project Start Date]@row) = 6, "June", IF(MONTH([Project Start Date]@row) = 7, "July", IF(MONTH([Project Start Date]@row) = 8, "August", IF(MONTH([Project Start Date]@row) = 9, "September", IF(MONTH([Project Start Date]@row) = 10, "October", IF(MONTH([Project Start Date]@row) = 11, "November", IF(MONTH([Project Start Date]@row) = 12, "December")))))))))))) + " " + YEAR([Project Start Date]@row), "")

    Frank Smith, PMP

    Assistant Director | IT Special Projects Mgr.

    Oregon Parks & Recreation Department

    If my response helps, please mark it as an accepted answer. 😎

  • Morris R
    Morris R ✭✭✭✭

    Thank you both

    @Andrée tried that one first and worked as expected

    Thank you very much!

  • Andrée Starå
    Andrée Starå ✭✭✭✭✭✭

    @Morris R

    Excellent!

    Happy to help!

    SMARTSHEET EXPERT CONSULTANT & PARTNER

    Andrée Starå | Workflow Consultant / CEO @ WORK BOLD

    W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35

    Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.