ClaireWallace
✭✭✭✭
Hello! How can I calculate the number of workdays, minus holidays, between two project dates (i.e. the project start date and project end date)? I have read up on the WORKDAY formula, but I can't seem to make it work with my data.
I am trying to run a Schedule Variance calculation, and I'd like it to update live based on the changing project schedule.
Thank you!
Answers
-
Hi Claire, you may look into the formula function NETWORKDAYS()
https://help.smartsheet.com/function/networkdays
--Anson