Calculate workday duration between two dates?

ClaireWallace
✭✭✭✭
Hello! How can I calculate the number of workdays, minus holidays, between two project dates (i.e. the project start date and project end date)? I have read up on the WORKDAY formula, but I can't seem to make it work with my data.
I am trying to run a Schedule Variance calculation, and I'd like it to update live based on the changing project schedule.
Thank you!
Answers
-
Hi Claire, you may look into the formula function NETWORKDAYS()
https://help.smartsheet.com/function/networkdays
--Anson
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.2K Get Help
- 430 Global Discussions
- 150 Industry Talk
- 490 Announcements
- 5.2K Ideas & Feature Requests
- 85 Brandfolder
- 154 Just for fun
- 74 Community Job Board
- 500 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!